News

10460 ORF Departures Building Norfolk, VA

FCC is awarded the Construction Contract for renovations/additions of Departures Building at Norfolk International Airport. Scope of work consists of Demolition of two precast vestibules and portions of the existing building envelope. Remove two hydraulic elevators, modernization and renovation of two existing elevators. One passenger and one freight.
Construction of 2 new two-story vestibule expansions, each with new hydraulic passenger elevators. The expansions will be precast panel on structural steel framing and glazed curtain walls. Project Value $2.7M

10454 W91236-18-B-0014 Renovate 60C Building, Richmond, VA.

FCC is awarded the Construction Contract for renovations of warehouse 60 at Defense General Supply Center Richmond.
Project consists of major renovation and repair encompassing the entire low-roof addition to Warehouse 60C. Construction to include New Roofing, Windows and Doors, Interior renovations of walls, ceilings, floors, Mechanical, Plumbing, Electrical, Low Voltage, Fire Alarms and Sprinklers as well as a complete Furniture Package. Project Value $1.8M

Bliley’s Funeral Home Chippenham Chapel Richmond, VA

6/29/2017 FCC is awarded the Add/Alterations of the Bliley’s Facility on Hull Street Road. Interior and Exterior Renovations to include all new interior finishes, replacement of  exterior façade finishes and exterior landscaping, asphalt pavement repairs, new storefront systems, and structural changes. Construction Investment is $2.5M

7/19/2017 Phase I of the interior scope is under way. All inspections have been released and finishes are starting to take place.

Project Completed May 2018

 

2 & Grace Street Parking Deck Facade Restoration Richmond, VA

FCC is awarded the Contract for the Renovations and Structural Repairs to the 2nd and Grace Street Parking Deck. The scope of work includes Rebuild brick veneer.  Tuck-pointing of brick masonry. Replace shelf angles. Drill new weep holes. Install new clip connections at CMU tops. Reconstruction of reinforced CMU wall. Reset precast coping panels. Roofing replacement. Power wash brick façade.

BYRD PARK, Monumental Window & Door Project Richmond, Va

12/22/2017

FCC is awarded the Contract for the Renovations at Byrd Park. The scope of work include, but are not limited to removal, replacement and restoration of existing windows and exterior doors at the Byrd Park Reserve Pump Station located at 1708 Pumphouse Road. Project Value $300K.

Exterior renovations to the LYCEUM Alexandria, VA

12/7/2017

FCC is awarded the Contract for Exterior Renovations to the Lyceum: Alexandria’s History Museum. The Lyceum is a historic building that was constructed in 1839. Currently, the building serves as both a museum and a learning center.  The operating hours for the facility are Monday through Saturday from 10:00 a.m. until 4:00 p.m., EST. The facility shall remain fully-functional during the Construction process and must be accessible during operational hours. This project includes demolition, exterior painting of building and window areas, stucco repair, replacement of damaged wood trim, caulking, carpentry, door hardware maintenance, and gutter and downspout inspection/repair.  All historic work completed within this project shall fall under the purview of the Building Architectural Review (BAR).

5/1/2018 Work in Progress.  Construction has Started.

 

Benedictine College Prep Weight Room, Goochland Co. VA

5/10/2017  FCC is awarded to Construct  a new 5775 sq. ft. Steel & Masonry Building.  This is a Design Build  construction project of the Athletic Facility. Project completion is set for June 2017. The Value of this project is over $800K but thanks to the Support of eTech Mechanical, RJ Smith Companies and First Class Contracting all donating substantial efforts to the cause, the concept was brought to reality for this much needed facility. Go Cadets!

The Design team is led by Amy Reineri of Casa Architecture, Civil Engineering by Hulcher & Associates, Structural Engineering by TAM Cornwell, Mechanical Engineering by eTech Mechanical, and Engineer on Record for Inspections is Zannino Engineering. Representing the GC is Tom White, Senior Project Manager.

Project is led by Tom White, Senior Project Manager.

6/15/2017 Progress is finally evident once we achieved the final design and permit process. Site work is under way, underground utilities, foundations and building pad is complete. Structural steel and masonry is in progress.

November 2017 Project Completed

 

New Kent Middle School, New Kent County Va

5/27/2017   FCC is awarded the Construction contract for the New Kent Middle School Addition. The project consists of building additions/alteration of a second floor structure to the existing building. The project value is over $1M and the completion schedule is 180 days

7/14/2017 – Work in Progress at the Middle School. The Project is 84 Days ahead of Schedule in an effort to complete the project prior to school starting in the fall.

October 2017 – Project Completed