News


VDOT Old Charlottesville Residence Hdqtrs, Charlottesville, VA

5/17/2017  FCC is awarded the construction to include Interior Renovations and Roof Replacement to include metal joists, Electrical, Plumbing and Mechanical. The project schedule is 180 Days and the value is $800K.

7/17/2017 – Demolition is almost complete. Project is 22 Days ahead of schedule.

Garrett Street Improvements Charlottesville, VA

12/16/2016 FCC is awarded the Contract for site improvements at Garrett Street Park. The project is scheduled to start early summer of 2017.

The scope of work will consist of removing existing stairs on Garrett Street and replacing stairs and landings as shown on construction drawings.

7/19/2017 – After many unforeseen conditions on the site and re-evaluation of some design elements, the project is well under way.

Tonsler Park Improvements Charlottesville, VA

10/25/2016  FCC is awarded the contract for the improvements to Tonsler Park.

The scope of work will be consistent with the attached plans and include the proper staking of the proposed stairs; clearing and site work within the construction location; forming and pouring of a full set of concrete stairs with handrails and a short section of walkway to provide a connection to an existing walkway. This is a steep site with a significant change in elevation from 5th Street to the walking path. The project also includes modification to an existing VDOT installed guard rail on 5th Street

3/16/2017 Progress is moving forward now that the weather has settled

6/30/17 – Project Completed. Superintendent Alex Loving with another successful project.

10295 Hunters Chase Roofing/Siding Project, Chesterfield VA

5/28/2017 FCC is awarded the Exterior Building Envelope Improvements for 5 buildings at Hunter’s Chase Apartments. Scope of work is inclusive of replacement of siding and roofing. This is the second phase of a project awarded to FCC.

6/18/2017 Project Completed.

Richmond Coliseum Fall Protection Project, Richmond VA

10/26/2016 – FCC is awarded the contract for Coliseum Fall Protection. The Scope of work  will consist of the installation of structural steel supports for fall protection lifelines, the installation of an inclined lifeline fall protection system, furnishing personal fall protection equipment required for use of the installed lifeline, testing and certification of the installed lifeline, and training on the new system. Project value is $500K

6/10/2017 Project Completed.

Suffolk Fire Station 1 Suffolk, VA

9/1/2016  FCC is awarded the Contract for Renovations of the existing Fire Station #1 located at 400 Market Street. Work includes a new parking area adjacent to the building and site work associated with the renovation. Interior renovation includes interior layout changes and removal and replacement of all interior finishes along with upgrades to the mechanical, electrical and plumbing systems. Work on the building exterior includes new windows and doors. Project value $ 2 M.

6/1/2017  Project Completed

IGT Va Lottery Data Center Expansion Richmond, VA

FCC is awarded the add/alterations Contract for the IGT/Va Lottery Data Center Project in Richmond. The Projct consists of Renovations to 18K Sq. Ft. of Office Space, Warehouse renovations and expansion of the current data center facility. Project is scheduled for completion on or about January 2017. Project value is north of $.5M

3/1/2017 – Final Completion to include additional warehouse items requested by the Owner.

WHSE 15, Defense General Supply Center Richmond, VA

FCC is awarded the contract for construction of Docks and Slabs at DSCR Whse 15. The Army Corps of Engineers Code W91236 is part of the American Infrastructure Program. The project consists of Site and Structural Concrete Construction. Scope of work is estimated to be north of $1.5M. Project is intended to start on February 2016 and expected completion is scheduled for 14 months.

7/14/2016 – After a late start on Construction due to tenant relocations, the project started late June 2016. Phase I is underway and progress is substantial.

WIP

2/25/2017 – Progress is ahead of schedule by 4 months. An additional Warehouse Bay was added to the contract. YTD, we have removed 4K Tons of concrete and replaced with new.

 

4/25/2017 – Project Completed. 94 Days ahead of schedule

DGS WH 15

Contractor Evaluation : WH 15 Evaluation

Jamestown Visitor Center, Williamsburg, VA

Jamestown ProgressFCC is awarded the contract for Lobby Repairs at Jamestown Settlement, VA. The project is  generally described as replace existing wood beams with glue laminated beams. Project Value $100K.

2/15/2017 – Construction has began on the replacement of the structural beams.Jamestown Progress

Jamestown Progress

 

American Honda Marine Training Center Richmond, VA

FCC is awarded the Construction of the New training facility for American Honda Marine. The facility will consist of Construction of a training center for marine technicians, offices and classrooms. The Richmond center will serve as a regional training center for marine technicians in order to keep up with their certifications with the rapid development marine outboard engine industry.